Reading Time: 1 minutes
The Nordex Group has landed a major new order in Latvia, securing the supply and installation of 21 N163/6.X turbines for the 147 MW Pienava wind farm—set to become the largest wind project in the country to date.
The project was developed by Eolus, a leading renewable energy developer in Scandinavia, and has been sold to Latvenergo, Latvia’s state-owned energy company.
Located in the Tukums municipality, southwest of Riga, the wind farm will feature Delta4000 series turbines mounted on 169-meter tubular steel towers, designed in a cold climate version. Turbine delivery and installation will begin in summer 2026, with commissioning scheduled for March 2027.
Following commissioning, Nordex will take on a 15-year maintenance contract, ensuring long-term reliability and performance.
Having entered the Latvian market only in 2024 with a 109 MW project, Nordex now has 300 MW under construction, rapidly expanding its footprint in the region’s growing renewable energy sector.