Tata Power Renewable Energy Limited (TPREL), a subsidiary of Tata Power, has commissioned its 100.8 MW wind power project in Ausa, Latur district, Maharashtra. The project will supply renewable electricity to Tata Power Mumbai Distribution (TPC-D), supporting the integration of clean energy into the region’s power supply.
The project is expected to generate approximately 308 million units (MU) of electricity annually and reduce carbon dioxide emissions by around 252,560 tonnes per year, contributing to Maharashtra’s renewable energy development and decarbonisation efforts.
The wind farm comprises 28 Horizontal Axis Wind Turbine Generators (WTGs) of the SG 3.6-145 model, each with a capacity of 3.6 MW, designed to support efficient renewable power generation.
During project execution, TPREL encountered a significant challenge when the grid connectivity plan was revised, requiring the Extra High Voltage (EHV) line configuration to be changed from underground cables to monopole structures. This marked the first-of-its-kind monopole EHV line installation undertaken by TPREL’s Wind Project Execution Division. Despite the additional design, procurement and execution complexities, the company completed the revised configuration without affecting the overall project schedule.
Following the commissioning of the Ausa Wind Project, TPREL’s total renewable utility capacity has reached 12.1 GW, including operational and under-development projects. Of this, 7.3 GW is operational, comprising 5.9 GW of solar and 1.4 GW of wind capacity, while the remaining 4.8 GW is under various stages of implementation.
The commissioning further expands Tata Power Renewables’ wind energy portfolio and strengthens its contribution to India’s growing renewable energy capacity.